Westgate - Water Main Replacement Project Reminder

START DATE:

Jul 10, 2025 11:00 AM

END DATE:

Jul 23, 2025 12:00 PM
Hello. This is a courtesy message from Community Utilities of Pennsylvania, your local water utility provider at 1-800-638-0262. This is a reminder that a water line replacement project started on Monday, February 10, 2025, and is still in progress. This is being considered Phase 1 of a multi-year phased approach to update aging infrastructure, as well as enhance fire protection in the area.

Construction activities will be performed by JOAO Bradley Construction of Bethlehem, Pennsylvania. Work will be conducted Monday through Friday between 7am and 4pm. Remaining work includes the repair and repaving of areas disturbed during the water line replacement. During paving and surface restoration activities, some traffic impacts are expected. Flaggers and appropriate signs will be in place if traffic needs to be redirected during this restoration phase.

The areas where these activities will take place are: Lane Avenue between Schoenersville Road and Winston Road, Statten Avenue between Schoenersville Road and Jacksonville Road, Winston Road between Lane Avenue and Statten Avenue and between Statten Avenue and Jacksonville Road, and Schoenersville Road between Roselawn Drive and the Schoenerserville and Jacksonville intersection.

Any impact to lawns or driveways as a result of the project will be restored to their former conditions. We appreciate your patience and apologize for any inconvenience you may experience while we work to provide you with the best possible water quality and service.