Blue Granite Water Company and Charlotte Water are in the progress of constructing the drinking water interconnection in the Lake Wylie community.

Crews from Charlotte Water have started construction in this area so please anticipate road closures. Below is a short project update from Charlotte Water. 

Project Update:
Charlotte Water (CLTWater) will install pipe to connect to Blue Granite Water Company (BGWC) near the Buster Boyd Bridge on York Road in South Carolina. This important interconnection will provide BGWC with additional water to serve the area.

  • Construction start: mid-August
  • Construction completion: November

Crews will start by tunneling under York Road at Blucher Circle (near QuikTrip) and work in one of the southbound / Charlotte bound lanes of York Road. One lane will be open each direction on York Road. 

Please check this link for additional information and how to contact Charlotte Water:
Drinking Water Interconnection Project